What Construction is Happening?

Private Construction Projects

If there are no parking signs on your block and you are wondering what type of work may be happening, you can search for permits associated with the address. The permit will include a phone number that you can use to ask questions.

Be wary of treating the dates on the permit as the exact dates of work. Oftentimes, this time range is longer than the actual work to give flexibility in case of inclement weather. The best way to get an exact range of dates for work is by calling the phone number listed on the permit. If your question isn’t answered here, please check our help desk article on construction.

Public Construction Projects

Below is a list of ongoing public construction and infrastructure projects in the 47th Ward, as well as a map locating those projects. If you have any questions regarding any of these projects, or if you want to receive email updates on a specific project, email josh@aldermanmartin.com or call (773) 868-4747.

Ongoing Public Infrastructure Projects

Lincoln Square Plaza and Parking Lot Pedestrian Improvements

Building off the Lincoln Square Ravenswood Chamber of Commerce’s 2019 Master Plan, Alderman Martin has worked with the community and CDOT to make large-scale improvements to the heart of Lincoln Square, aimed at improving the pedestrian and cyclist experience in the area around the Western Brown Line station, as well as ensure that that area is better suited to welcome the many festivals that take place there each here.

The planned improvements are visible in this CDOT presentation. They will target the “Farmers Market” parking lot and the plaza adjacent to the El station. Those spaces, as well as Leland Ave itself will be raised to provide one continuous pedestrian space that is easily convertible for events. The space under the El tracks from Lincoln to the station will be improved with better paving and lighting. A bidirectional protected bike lane will allow cyclists to travel east and west along Leland.

Our office hosted a virtual community meeting on 12/17/24 with the construction team to present on the upcoming construction process, which will last until the summer. You can review a recording of that meeting here.


***

Update (9/3/25):

  • Western Ave: Crews are now work on the curbs on the west side of Western, both north and south of Leland. They are rebuilding sidewalks and curbs, building a bus bulb on the southwest corner, and preparing the installation of new lights and traffic signals. Sidewalks and businesses on the west side will remain accessible. They hope to complete this work in another 5 weeks.

    Please note that the southbound #49 bus stop is closed for the duration of this work. Riders can catch the bus at Lawrence or at Wilson.

  • Pavers: Crews intend to install pavers in sidewalks and by crosswalks along Lincoln and Leland over the next two weeks.

  • Paving: Crews plan to mill and pave Leland, Lincoln, and the space under the tracks throughout the second half of September.

  • Parking Lot: Crews will be pouring the concrete base on the parking lot over the next two weeks. This will then allow them to install the pavers on the surface of the parking lot.

  • CTA Western Station: The CTA is starting demolition work on the bus turnaround this week. The work will take place overnight several nights in a row for safety reasons.

    CTA is also beginning to replace exterior masonry on the north and east sides of the building. To allow that work to happen, they must close off direct pedestrian access between the station and Lincoln Ave.

***

The impact on traffic to Western Ave in the mornings, while temporary and inevitable as part of this project, has highlighted the difficult that westbound traffic has in moving through the Western & Wilson intersection. As such, Alderman Martin is pleased to have allocated the necessary funds to install a new left-turn arrow from Wilson onto Western.


Ashland Avenue is slated to be repaved starting later this month from School to Clark. This repaving will involve improvements to pedestrian safety, including curb extensions and refuge islands, as well as bus bulbs benefiting the #9 bus.

You can watch a recording of our 8/21 meeting with the 40th Ward here.

Update (9/5/25):

Work is underway on the first segment of the resurfacing of Ashland Ave, between School St and Montrose Ave.

Crews finished milling (removing the asphalt) and are laying the first of two layers of asphalt. They currently expect to finish that work either Monday or Tuesday.

Once that is done, CDOT has agreed to remove as many signs as possible to return parking to the area.

Signs will remain where work is planned for the next phase on this segment, which includes up to 4 weeks of:

  • Sidewalk replacement

  • Curb replacement

  • Street patching

  • Utility structure (manhole) adjustments.

Ashland Arterial Resurfacing


The Department of Water Management is working on replacing 1,300 of water main beneath Hutchinson (Greenview to Clark) and Greenview (Berteau to Cullom). The water main is the large pipe that runs along the street and brings water to each building's individual service line. The existing main dates back to the 1890s. This project will be an opportunity for DWM to replace the water main, replace any existing lead service lines, and fully repave all three blocks once the project is complete. The project is expected to last approximately 3 months. Impacted residents must abide by the parking restrictions and be on the lookout for direct phone outreach from the Water Department regarding their personal lead line.

  • Expected Duration of Project: 3 months (July completion), followed by asphalt and concrete restoration.

  • Parking impacts: 7am-3:30pm on weekdays – no access to or parking on the street. Parking will be available at all other times. Crews will work to accommodate special deliveries, disabled residents, etc.

  • Water Shutoffs: Crews will strive to provide 5 days' notice ahead of any scheduled service interruptions. Some emergency repairs may take place (old pipes tend to crack as they are being worked on). These service interruptions are not expected to impacted buildings that are not on the directly impacted blocks.

Update (9/5/25):

The Water Department has completed the entirety of their water main replacement on Greenview and on Hutchinson, including transferring all buildings' services transfers.

The restoration contractor finished concrete repairs and repaved the streets. They are proceeding with parkway restoration.

Greenview - Hutchinson Water Main Replacement


The Department of Water Management is planning on replacing the main beneath:

  • Hermitage from Sunnyside to Montrose

  • Sunnyside from Paulina to Ravenswood

  • Ravenswood (west leg) from Wilson to Lawrence.

The water main is the large pipe that runs along the street and brings water to each building's individual service line. The existing main dates back to the 1890s. This project will be an opportunity for DWM to replace the water main, replace any existing lead service lines, and fully repave all three blocks once the project is complete. The project is expected to last approximately 3 months. Impacted residents and businesses must abide by the parking restrictions and be on the lookout for direct phone outreach from the Water Department regarding their personal lead line.

  • Start Date: Crews intend to start work after Memorial Day.

  • Expected Duration of Project: 3 months, followed by asphalt and concrete restoration.

  • Parking impacts: 7am-3:30pm on weekdays – no access to or parking on the street. Parking will be available at all other times. Crews will work to accommodate special deliveries, disabled residents, etc.

  • Water Shutoffs: Crews will strive to provide 5 days' notice ahead of any scheduled service interruptions. Some emergency repairs may take place (old pipes tend to crack as they are being worked on). These service interruptions are not expected to impacted buildings that are not on the directly impacted blocks.

You can watch a recording of our 5/19 meeting with the Water Department here.

Update (9/5/25):

  • 4700 Ravenswood: Asphalt restoration to be completed at the same time as the next block south.

  • 4600 Ravenswood: The Water Department has completed all their work and vacated this block! Restoration crews will move in shortly to begin repairing concrete.

  • 4400 Hermitage: The new water main is installed and has been chlorinated. Starting next week, two crews (the one from Ravenswood is joining efforts on Hermitage!) will start transferring buildings' services to the new main. They expect this work to take 3-4 weeks.

  • Sunnyside: Crews have finished their work on Sunnyside for now. At the very end of the project, they will return for final work in the intersection of Ravenswood & Sunnyside.

Ravenswood, Hermitage, Sunnyside Water Main Replacement


Western Ave Arterial Resurfacing

Alderman Martin worked with Ald. Vasquez to secure the funding for CDOT to resurface Western Ave from Foster to Waveland.

The work will involve grinding down the existing asphalt, raising manholes and other utility services to meet the street level, and repaving the streets with new asphalt. This will include replacing the asphalt on the street and replacing ADA ramps as well as damaged sidewalks.

Pedestrian safety improvements will include curb extensions and refuge islands. CDOT will also be making improvements to transit facilities, including bus bulbs and bus-only lanes. Transit and pedestrian improvements on Western will extend as far south as George St.

On 8/14 our office, along with CDOT and the 40th Ward, hosted a virtual meeting to discuss the work and address any concerns that residents or businesses may have. You can view a recording of this meeting here.

Update (6/26/25):

This repaving project was completed in May. Crews are proceeding with final punchlist items to wrap up the project.


Alderman Martin worked with Ald. Vasquez to secure the funding for CDOT to resurface Damen Ave from Wilson Ave north to Farragut.

The work will involve grinding down the existing asphalt, raising manholes and other utility services to meet the street level, and repaving the streets with new asphalt. This will include replacing the asphalt on the street and replacing ADA ramps as well as damaged sidewalks.

On Damen, CDOT will also be making pedestrian safety improvements in the form of curb extensions and raised intersections at Leland and at Winnemac. They will also include improvements to bicycle facilities.

On 8/14/24 our office, along with CDOT and the 40th Ward, hosted a virtual meeting to discuss the work and address any concerns that residents or businesses may have. You can view a recording of this meeting here.

Update (7/25/25):

Paving is complete on Damen and concrete work are complete on Damen south of Foster. Crews will complete punch list items once they wrap up the portions farther north. This will include repainting the concrete intersection of Damen & Leland.

Damen Ave Resurfacing (north)


Giddings Plaza is a staple of the community and has been well-loved for decades. However, the condition of the plaza has worsened over the years, with missing pavers and tripping hazards that make the plaza difficult to navigate for our seniors, young children, and disabled residents. 

Starting on August 12th, CDOT will begin work to remove and replace the pavers on the plaza to eliminate these tripping hazards. The work will replace all the pavers, remove the broken water fountain (behind a bench near Jerry’s) to be replaced with a planter, and remove one of the trees in the plaza due to its health and impact on the pavers. 

After consulting with nearby businesses, our office coordinated with CDOT and the project contractor to create a plan that would have the least impact on the surrounding businesses, residents, and users of the plaza. The updated plan divides the plaza into 5 sections for the work to be completed in a phased manner.

Crews will work on one section of the plaza at a time – working from Lincoln back toward the alley – leaving the rest of the plaza open for pedestrian traffic. This phased approach will allow the plaza to still be partially accessible for pedestrians and residents, and will have the least amount of impact on the adjacent businesses and sidewalk cafés. During each phase, a 6-foot-fence will be put up along the perimeter of the relevant section to guarantee neighbors' safety. Equipment and materials will be brought from behind the plaza, but the alley will remain accessible throughout.

Update (5/15/25):

Work was largely completed.

The contractor still needs to complete punch list items over the past couple of weeks. They intend to return to remove pavers on the southeast corner of the plaza to build a new raingarden to address consistent standing water issues.

Giddings Plaza Paver Replacement


Alderman Martin helped the CTA secure $20M to proceed with a large-scale renovation of the Western Brown Line station, which will take place in 2024 and 2025.

The Alderman and the CTA have co-hosted two community meetings to help shape the work; you can read reporting about the first meeting here. You can also view a recording of the second meeting, hosted on 5/29/24, at this link.

Update (8/29/25):

Our office was just informed that the CTA plans to begin demolition in the bus turnaround area south of the Western Plaza, including the bus canopy itself. The CTA has opted to conduct this work overnight next week.

Work will take place during nighttime hours, 9:00 pm to 5:00 am, starting Wednesday September 3, 2025. The work will take 3 to 4 nights to complete.

Western Brown Line Station Improvements


Cornelia Collector Resurfacing

As part of its Collector Resurfacing program, CDOT is repaving Cornelia Ave between Paulina St and Western Ave.

Update (7/10/25):

Collector has been successfully repaved.


The Department of Transportation is building the Leland Neighborhood Greenway from Rockwell Ave to Clark St. This low-stress bikeway slow traffic for the benefit of cyclists and pedestrians and will allow cyclists to safely bike from the lake to the river. Improvements will include:

  • bike-friendly speed humps;

  • detached curb extensions (bump-outs), landscaped west of Western;

  • a contraflow bike lane on one-way stretches to allow cyclists to travel in both directions;

  • raised crosswalks;

  • a protected bike lane and traffic diverter between Lincoln and Western.

You can find out more about the project here.

Update (7/9/25):

Crews are building the final part of the project – a protected bike lane between Lincoln and Western – as part of the Western Plaza renovation work at that intersection.

Leland Neighborhood Greenway


As part of its Collector Resurfacing program, CDOT plans to repave Ravenswood Ave north of Wilson Ave. In addition to the repaving, CDOT will install a number of pedestrian and bicycle improvements along the corridor. As discussed at our 5/1/24 community meeting (which you can read reporting on here), CDOT will install a southbound contraflow bike lane between Winnemac and Leland, part of which will be protected by a concrete curb between Ainslie and Winnemac (replacing the parking on the west side of Ravenswood). Additionally, two raised crosswalks will be installed between Lawrence and Winnemac and a pedestrian refuge island on Lawrence at Ravenswood to improve visibility and safety for crossing pedestrians.

Finally, this project will create space for the planned expansion of the Winnslie Parkway community garden from Ainslie to Lawrence. This will provide 1,000 new feet of pedestrian paths to the Ravenswood Metra Station in a new community-run garden (see here). To accommodate these improvements, CDOT will convert diagonal parking into parallel parking spaces along the tracks on the west side of Ravenswood between Ainslie and Lawrence. This will result in a reduction of roughly 25 parking spaces on that stretch. 

Construction is expected to begin on 5/26. Crews will first work on curbs (repairing them and proceeding with the parkway expansion mentioned above) for several weeks, starting at Peterson and moving south. They will then remove the old asphalt and repave the street – expect a 2-3 week delay between those two actions, as utility companies repair and adjust manholes and other structures. They will finally return at the end of the project to install the bike lane curb between Ainslie and Winnemac, refuge island at Lawrence, and raised crosswalks. Please note that CDOT anticipates temporary closures of Ravenswood north of Lawrence for the construction of the raised crosswalks.

Update (8/21/25):

Crews will starting paving Ravenswood tomorrow. They will start at Wilson and work their way north; they expect to reach at least Ainslie by the end of the day.

Parking restrictions will be in place until the following week when they restripe the street. They will then be able to remove the parking restrictions until the next phase of work.

Ravenswood Ave Collector Resurfacing