What Construction is Happening?

Private Construction Projects

If there are no parking signs on your block and you are wondering what type of work may be happening, you can search for permits associated with the address. The permit will include a phone number that you can use to ask questions.

Be wary of treating the dates on the permit as the exact dates of work. Oftentimes, this time range is longer than the actual work to give flexibility in case of inclement weather. The best way to get an exact range of dates for work is by calling the phone number listed on the permit. If your question isn’t answered here, please check our help desk article on construction.

Public Construction Projects

Below is a list of ongoing public construction and infrastructure projects in the 47th Ward, as well as a map locating those projects. If you have any questions regarding any of these projects, or if you want to receive email updates on a specific project, email josh@aldermanmartin.com or call (773) 868-4747.

Ongoing Public Infrastructure Projects

Lincoln Square Plaza and Parking Lot Pedestrian Improvements

Building off the Lincoln Square Ravenswood Chamber of Commerce’s 2019 Master Plan, Alderman Martin has worked with the community and CDOT to make large-scale improvements to the heart of Lincoln Square, aimed at improving the pedestrian and cyclist experience in the area around the Western Brown Line station, as well as ensure that that area is better suited to welcome the many festivals that take place there each here.

The planned improvements are visible in this CDOT presentation. They will target the “Farmers Market” parking lot and the plaza adjacent to the El station. Those spaces, as well as Leland Ave itself will be raised to provide one continuous pedestrian space that is easily convertible for events. The space under the El tracks from Lincoln to the station will be improved with better paving and lighting. A bidirectional protected bike lane will allow cyclists to travel east and west along Leland.

Our office hosted a virtual community meeting on 12/17/24 with the construction team to present on the upcoming construction process, which will last until the summer. You can review a recording of that meeting here.


***

Update (7/17/25):

The 6-week closure of Leland at Lincoln continues (see details below).

  • Intersection of Leland & Lincoln: Crews are completing the necessary water work in the intersection this week and next, before they can start rebuilding the intersection and sidewalks east of Lincoln. They are 3 weeks away from reopening the crosswalk across Leland to pedestrians (2 weeks beyond that for the concrete to be strong enough to vehicles to use the intersection).

  • South Side of Leland: Crews have started demolition along the south side of Leland between Lincoln and Western, where they will be pouring a new curb and gutter shortly. This will require closing the crosswalk across Leland on the east side of Western. Pedestrians will need to cross Western, then Leland, then Western again instead while this crosswalk is closed.

  • Western Ave: Crews installed new sidewalks along Western north of the El station, which they intend to open to pedestrians next week.

  • Parking Lot and CTA Bus Turnaround: Crews are continuing demolition and removals in the CTA bus turnaround and the parking lot. They aim to pour back the pavement of the bus turnaround in the next 2 weeks.

Closure of Leland at Lincoln

  • Start date: Tuesday 6/24

  • Duration: 6 weeks (weather dependent).

  • Lincoln: closed to traffic between Leland and Eastwood.

  • Leland: closed at Lincoln.

  • Leland Ave between Western and Lincoln: temporarily converted to one way westbound only.

  • Pedestrian access will be maintained to all businesses and the Brown Line

***

The impact on traffic to Western Ave in the mornings, while temporary and inevitable as part of this project, has highlighted the difficult that westbound traffic has in moving through the Western & Wilson intersection. As such, Alderman Martin is pleased to have allocated the necessary funds to install a new left-turn arrow from Wilson onto Western.


The Department of Water Management is working on replacing 1,300 of water main beneath Hutchinson (Greenview to Clark) and Greenview (Berteau to Cullom). The water main is the large pipe that runs along the street and brings water to each building's individual service line. The existing main dates back to the 1890s. This project will be an opportunity for DWM to replace the water main, replace any existing lead service lines, and fully repave all three blocks once the project is complete. The project is expected to last approximately 3 months. Impacted residents must abide by the parking restrictions and be on the lookout for direct phone outreach from the Water Department regarding their personal lead line.

  • Expected Duration of Project: 3 months (July completion), followed by asphalt and concrete restoration.

  • Parking impacts: 7am-3:30pm on weekdays – no access to or parking on the street. Parking will be available at all other times. Crews will work to accommodate special deliveries, disabled residents, etc.

  • Water Shutoffs: Crews will strive to provide 5 days' notice ahead of any scheduled service interruptions. Some emergency repairs may take place (old pipes tend to crack as they are being worked on). These service interruptions are not expected to impacted buildings that are not on the directly impacted blocks.

Update (7/10/25):

Crews have completed the final service transfer on Hutchinson, meaning that the new main is fully installed and active on that block.

Crews have started transferring services to the new water main under Greenview. They hope to complete those by the end of July.

Final restoration (asphalt, concrete, and parkways) will take place once Greenview is complete. In the meantime, most parking restrictions have been removed from Hutchinson, except for a small remaining staging area.

Greenview - Hutchinson Water Main Replacement


The Department of Water Management is planning on replacing the main beneath:

  • Hermitage from Sunnyside to Montrose

  • Sunnyside from Paulina to Ravenswood

  • Ravenswood (west leg) from Wilson to Lawrence.

The water main is the large pipe that runs along the street and brings water to each building's individual service line. The existing main dates back to the 1890s. This project will be an opportunity for DWM to replace the water main, replace any existing lead service lines, and fully repave all three blocks once the project is complete. The project is expected to last approximately 3 months. Impacted residents and businesses must abide by the parking restrictions and be on the lookout for direct phone outreach from the Water Department regarding their personal lead line.

  • Start Date: Crews intend to start work after Memorial Day.

  • Expected Duration of Project: 3 months, followed by asphalt and concrete restoration.

  • Parking impacts: 7am-3:30pm on weekdays – no access to or parking on the street. Parking will be available at all other times. Crews will work to accommodate special deliveries, disabled residents, etc.

  • Water Shutoffs: Crews will strive to provide 5 days' notice ahead of any scheduled service interruptions. Some emergency repairs may take place (old pipes tend to crack as they are being worked on). These service interruptions are not expected to impacted buildings that are not on the directly impacted blocks.

You can watch a recording of our 5/19 meeting with the Water Department here.

Update (7/17/25):

  • 4700 N Ravenswood: Work is just about complete between Lawrence and Leland! Early next week, Water crews will clean up the block and move on fully to the next block south. Please note that restoration crews will follow right behind them (expected week of 7/28). They will rebuild impacted curbs and sidewalks before repaving the street to fully reopen it.

  • 4600 N Ravenswood: Water work will begin in earnest next week. Crews will begin laying the water main down the block from Leland to Wilson.

  • Sunnyside: Work is fully complete on Sunnyside between Ravenswood and Hermitage. Restoration crews will move in shortly to begin repairing concrete curbs before they can repave the block. The block of Sunnyside between Hermitage and Paulina still contains two outstanding Lead Service Line Replacements before it too can be restored.

  • 4400 N Hermitage: Water work has started on this block. Crews are replacing Private Drains where necessary before they begin installing the new water main.

Ravenswood, Hermitage, Sunnyside Water Main Replacement


Western Ave Arterial Resurfacing

Alderman Martin worked with Ald. Vasquez to secure the funding for CDOT to resurface Western Ave from Foster to Waveland.

The work will involve grinding down the existing asphalt, raising manholes and other utility services to meet the street level, and repaving the streets with new asphalt. This will include replacing the asphalt on the street and replacing ADA ramps as well as damaged sidewalks.

Pedestrian safety improvements will include curb extensions and refuge islands. CDOT will also be making improvements to transit facilities, including bus bulbs and bus-only lanes. Transit and pedestrian improvements on Western will extend as far south as George St.

On 8/14 our office, along with CDOT and the 40th Ward, hosted a virtual meeting to discuss the work and address any concerns that residents or businesses may have. You can view a recording of this meeting here.

Update (6/26/25):

This repaving project was completed in May. Crews are proceeding with final punchlist items to wrap up the project.


Alderman Martin worked with Ald. Vasquez to secure the funding for CDOT to resurface Damen Ave from Wilson Ave north to Farragut.

The work will involve grinding down the existing asphalt, raising manholes and other utility services to meet the street level, and repaving the streets with new asphalt. This will include replacing the asphalt on the street and replacing ADA ramps as well as damaged sidewalks.

On Damen, CDOT will also be making pedestrian safety improvements in the form of curb extensions and raised intersections at Leland and at Winnemac. They will also include improvements to bicycle facilities.

On 8/14/24 our office, along with CDOT and the 40th Ward, hosted a virtual meeting to discuss the work and address any concerns that residents or businesses may have. You can view a recording of this meeting here.

Update (7/17/25):

Paving is complete on Damen. Crews are working on the final stage of the project, installing a raised intersection at Damen & Leland (as well as at Damen & Winona and Damen & Winnemac, in the 40th Ward). Raised intersections create a safe, slow-speed crossing and public space for improved pedestrian safety.

Having completed the west side of the intersection, crews are working on building the east side, with Damen closed to northbound traffic at Eastwood. I am pleased to say that they are already pouring the concrete starting today. They currently expect to be able to fully reopen the intersection to vehicle traffic early next week, completing this 4-week project in 2 weeks. They will still need to complete small asphalt work after that, but nothing that will require closing the intersection.

For the duration of the work, the #50 Damen bus in both directions will run on Ashland north of Montrose, connecting to its regular route at Ashland & Foster.

Damen Ave Resurfacing (north)


Giddings Plaza is a staple of the community and has been well-loved for decades. However, the condition of the plaza has worsened over the years, with missing pavers and tripping hazards that make the plaza difficult to navigate for our seniors, young children, and disabled residents. 

Starting on August 12th, CDOT will begin work to remove and replace the pavers on the plaza to eliminate these tripping hazards. The work will replace all the pavers, remove the broken water fountain (behind a bench near Jerry’s) to be replaced with a planter, and remove one of the trees in the plaza due to its health and impact on the pavers. 

After consulting with nearby businesses, our office coordinated with CDOT and the project contractor to create a plan that would have the least impact on the surrounding businesses, residents, and users of the plaza. The updated plan divides the plaza into 5 sections for the work to be completed in a phased manner.

Crews will work on one section of the plaza at a time – working from Lincoln back toward the alley – leaving the rest of the plaza open for pedestrian traffic. This phased approach will allow the plaza to still be partially accessible for pedestrians and residents, and will have the least amount of impact on the adjacent businesses and sidewalk cafés. During each phase, a 6-foot-fence will be put up along the perimeter of the relevant section to guarantee neighbors' safety. Equipment and materials will be brought from behind the plaza, but the alley will remain accessible throughout.

Update (5/15/25):

Work was largely completed.

The contractor still needs to complete punch list items over the past couple of weeks. They intend to return to remove pavers on the southeast corner of the plaza to build a new raingarden to address consistent standing water issues.

Giddings Plaza Paver Replacement


Starting in early June, CDOT will be making structural repairs to the Montrose bridge over the river. The work will include sidewalk improvements, bridge deck patching, milling and paving the existing asphalt pavement, and striping. During bridge deck patching, there will be closures on half of the bridge, and then flipped once complete, but traffic will shift and remain open in both directions during the work. Work is expected to be completed in early August

Montrose Bridge Repairs


Greenview/Cornelia Gas Main Replacement

Between October 2023 and September 2024, Peoples Gas is working to replace 3 miles of gas lines under the sidewalks along Cornelia (Ashland to Lakewood) and Greenview (Roscoe to Grace) in anticipation of a sewer replacement project planned for the area in 2025.

You can watch a recording of our 11/15/23 virtual community meeting with the 44th Ward and Peoples Gas by clicking here.

Update:

As of June 2024, construction crews are working on restoring sidewalks throughout the project boundaries. They expect to have the vast majority of sidewalks completed by late September.


The project itself will be completed toward the end of 2024, once all building connections have been completed and the old gas main can be taken offline.


Alderman Martin helped the CTA secure $20M to proceed with a large-scale renovation of the Western Brown Line station, which will take place in 2024 and 2025.

The Alderman and the CTA have co-hosted two community meetings to help shape the work; you can read reporting about the first meeting here. You can also view a recording of the second meeting, hosted on 5/29/24, at this link.

Western Brown Line Station Improvements


As part of its Collector Resurfacing program, CDOT is repaving Cornelia Ave between Paulina St and Western Ave.

Update (12/10/24):

In the fall of 2024, CDOT successfully replaced all the curbs along Cornelia. However, there was not enough time to complete the resurfacing before winter, so CDOT filled in all open holes along the curbs for the winter. They will repave Cornelia in the spring of 2025.

Cornelia Ave Collector Resurfacing


The Department of Transportation is building the Leland Neighborhood Greenway from Rockwell Ave to Clark St. This low-stress bikeway slow traffic for the benefit of cyclists and pedestrians and will allow cyclists to safely bike from the lake to the river. Improvements will include:

  • bike-friendly speed humps;

  • detached curb extensions (bump-outs), landscaped west of Western;

  • a contraflow bike lane on one-way stretches to allow cyclists to travel in both directions;

  • raised crosswalks;

  • a protected bike lane and traffic diverter between Lincoln and Western.

You can find out more about the project here.

Update (1/9/25):

Contractors have finished building the project’s bump-outs and striped the bike markings, including contraflow lanes. They will be installing speed humps in the spring, when they will also plant bump-outs that were filled with soil.

Crews will also build the protected bike lane between Lincoln and Western as part of the Western Plaza renovation work at that intersection.

Leland Neighborhood Greenway


As part of its Collector Resurfacing program, CDOT plans to repave Ravenswood Ave north of Wilson Ave. In addition to the repaving, CDOT will install a number of pedestrian and bicycle improvements along the corridor. As discussed at our 5/1/24 community meeting (which you can read reporting on here), CDOT will install a southbound contraflow bike lane between Winnemac and Leland, part of which will be protected by a concrete curb between Ainslie and Winnemac (replacing the parking on the west side of Ravenswood). Additionally, two raised crosswalks will be installed between Lawrence and Winnemac and a pedestrian refuge island on Lawrence at Ravenswood to improve visibility and safety for crossing pedestrians.

Finally, this project will create space for the planned expansion of the Winnslie Parkway community garden from Ainslie to Lawrence. This will provide 1,000 new feet of pedestrian paths to the Ravenswood Metra Station in a new community-run garden (see here). To accommodate these improvements, CDOT will convert diagonal parking into parallel parking spaces along the tracks on the west side of Ravenswood between Ainslie and Lawrence. This will result in a reduction of roughly 25 parking spaces on that stretch. 

Construction is expected to begin on 5/26. Crews will first work on curbs (repairing them and proceeding with the parkway expansion mentioned above) for several weeks, starting at Peterson and moving south. They will then remove the old asphalt and repave the street – expect a 2-3 week delay between those two actions, as utility companies repair and adjust manholes and other structures. They will finally return at the end of the project to install the bike lane curb between Ainslie and Winnemac, refuge island at Lawrence, and raised crosswalks. Please note that CDOT anticipates temporary closures of Ravenswood north of Lawrence for the construction of the raised crosswalks.

Update (7/17/25):

Having completed conrete work (fixing and replacing curbs) on the east side of the street, the contractor is currently working on the west side of the street.

North of Lawrence, this involves building curb extensions, as well as moving out the curb farther east – this makes space for the expansion of the Winnslie Greenway community garden south from Ainslie to Lawrence, with parking switching from diagonal to parallel parking.

This concrete work has geen delayed a bit, and the contractor now expects to have 3 more weeks of concrete work ahead of them. Once that is done, crews will be able to start repaving the street.

Ravenswood Ave Collector Resurfacing


The Department of Water Management intends to replace the water mains under Hermitage Ave from Montrose and Sunnyside and under Sunnyside Ave from Ravenswood to Paulina. This project is not yet scheduled.

Hermitage/ Sunnyside Water Main Replacement